Tank Farm Control System:

In April 2012, TRC was awarded a Turn-Key contract by Huade Petrochemical Co. in China, to build a Tank Farm Control System for a 31,000 m³ Crude Oil Storage Project.

The project includes 4 Crude Oil Tanks, 1 pumping Station and a Control Center upgrade. It comprises an expansion of the existing production monitoring system that TRC has installed in 2004, which includes a 20,000 m³ storage area and a 200 Km transmission pipeline control system. As part of this contract, TRC will replace the existing InSQL database server, supply a set of redundant Real-Time data servers and a redundant Allen Bradley Controllogix PLC system that includes a Fire & Gas system. In addition, TRC will implement a link to the SAAB Radar Tank Gauging System in order to include product movement into the SCADA System functionality. The contract is scheduled to be completed by October, 2012.